Zenon Expertise: Why Should the Commissioning Process Start Before Design?

3 days ago
2 min read

The Commissioning Process should begin at project inception, during the pre-design phase, before major design decisions have been made.


This is the perspective shared by Boyd England, Principal, Commissioning – Prairies at Zenon. His point is straightforward: before designing a building, we need to understand what the Owner expects it to do and how it needs to operate.


During pre-design, the Owner, supported by the Commissioning Provider, establishes the Owner's Project Requirements (OPR). These requirements should be measurable and address building performance, energy efficiency, occupant comfort, reliability, maintenance and day-to-day operations.


The design team is then responsible for developing a design that addresses those requirements.

As Boyd explains:


"It doesn't make much sense to wait until the building is designed to ask the Owner what they expect it to do. Those requirements should be established before the design decisions are made."

The Commissioning Process doesn't end once the requirements are established. It continues through design, construction, functional verification and occupancy.


During design, the Commissioning Provider evaluates how the developing design addresses the OPR and documents concerns for the design team to respond to. During construction, the focus includes verifying installations, reviewing contractor testing documentation and independently verifying system performance against the applicable requirements.


This provides the Owner with documented evidence of what has been verified, what remains outstanding and where further attention is required.


Starting the Commissioning Process early provides opportunities to identify and address concerns before they become construction problems, when changes can be more disruptive and expensive.


A Coordinated Approach at Westwood 7–12 Community High School Replacement

Fort McMurray, Alberta


Zenon is engaged as the Independent Commissioning Authority for the new Westwood 7–12 Community High School Replacement, with our involvement beginning during the design stage.

Our scope includes evaluating the Owner's requirements and reviewing the developing design across several disciplines, including the building envelope, mechanical, electrical, acoustical and building control systems.


These reviews provide an opportunity to identify potential performance, coordination and operational concerns while the design is still being developed, rather than discovering them after the systems have been installed.


As the project progresses, the Commissioning Process will provide the Owner with independent verification and documented findings against the applicable project requirements.

Westwood is an example of how involving the Commissioning Provider during design can help identify concerns before they carry forward into construction.


Getting Involved at the Right Time


The Commissioning Process is not something that should be introduced when equipment is ready for testing.


It should start when the Owner is establishing what the building needs to achieve, and continue through the project to verify that those expectations are being addressed.


The earlier the Commissioning Provider is involved, the greater the opportunity to identify concerns before they become costly problems.


At Zenon, our approach is to provide Owners with independent, documented verification throughout the Commissioning Process, while working with the project team to identify issues and ensure they are brought to the attention of those responsible for resolving them.


Connect with Zenon to discuss the Commissioning Process for your next project at zenongroup.com.